What it is

Each project keeps its list of materials on its Material Allocation stage, in the panel Procurement Management: "Manage procurement items and quantities for this project". Each line names an inventory item with its required, blocked, issued and remaining quantities.

The panel is locked while the project is Tender or Lost: it shows "Material allocation is locked". See Material allocation is locked.

How it moves

  1. The project is won. Accepting a quotation for a tender moves the project to Won, and the panel opens. See Accept or reject a quotation.
  2. Lines are added. Add them by hand, apply a saved template, or push a finalized BoQ. See Allocate materials to a project and Push a BoQ to procurement. The items chosen on the System Type Selection stage are marked in the Recommended column. See Save your equipment selection.
  3. Stock is blocked. A Block Quantity on a line keeps that stock for the project. It shows as Block qty for project on the Inventory page and Blocked Qty on Project Materials. See Block stock, change quantities or remove a line on a project's materials.
  4. Shortages show. Project Materials lists every item that projects need more of than you hold. See See material shortages across projects. Purchase orders for them are raised in the Purchase module. See Create a purchase order.
  5. Stock is issued. A project stock out issues the lines to the site. It updates the issued quantity on the project's lines and on Project Materials, and keeps the price at issue for the project's job costing (see How job costing works out a project's cost and margin). See Issue stock to a project.
  6. Items come back. Returned, damaged, consumed and lost quantities are recorded against the stock out. See Return issued items to inventory.

A stock-out line can also name a line of a material request, which it then fulfils. See Issue stock or raise a purchase order against a request line.

Who is involved

RoleWhat they do
Anyone with Approve on QuotationsAccepts the quotation that opens the panel.
Anyone who can see the Material Allocation stage (with Project Management: by default Owner, Admin, Manager, Technician and User) and has View on ProcurementsSees the panel. With Add they add lines; with Edit they block stock and change quantities.
Anyone with Inventory Management and Add on Stock outs (by default Owner, Admin and Manager)Issues the stock and records returns.
Anyone with Inventory Management and View on ProcurementsReads shortages on Project Materials.