Before you start

  • You need Project Management, you can see the project's Material Allocation stage, and you have Edit on Procurements. To remove a line, Delete on Procurements.
  • The project is not Tender or Lost.
  • The project has material lines. See Allocate materials to a project.

Steps

Block stock for the project

  1. Open the project's Material Allocation stage. From the project's Costing tab, Block stock opens it too.
  2. In the Procurement Items table, find the line. Available Qty shows what you can block.
  3. Change Block Quantity on the line.
  4. Save the change.

Change a line's quantities

  1. In the Procurement Items table, find the line.
  2. Change Required Qty, or the other quantities you need.
  3. Save the change.

Remove a line

  1. In the Procurement Items table, use the line's Actions to delete it. The box "Delete Procurement Item" opens.
  2. Confirm.

Result

Block stock for the project and Change a line's quantities: "Procurement item updated successfully" shows. Remaining Qty shows what is still to be issued. Blocked stock shows as Block Qty for Project on the Inventory page and Blocked Qty on Project Materials, and is kept for this project.

Remove a line: the line leaves the table.

Next: Issue stock to a project.