Before you start
- You need Project Management or Inventory Management, and Edit on Projects. Technicians and workers cannot save.
- The project has a System Type Selection stage.
- You chose at least one unit on the Choose card. See How AC unit recommendations work for the form your project uses.
Steps
-
Read the footer at the bottom of the screen: "Capacity: [selected] of [required] TR, [verdict] ([number] unit(s))" and "Airflow: [selected] CFM of [required] CFM, [verdict]".

Step 1. The footer with the capacity and airflow verdicts and Save selection. -
If a verdict reads short or oversized, change the quantities or units. See The verdict says short or oversized.
-
Select Save selection ([number] units). It reads "Saving..." while it saves.
-
To discard your changes instead, select Reset edits. The page goes back to the saved selection.
Result
The message "Saved [number] units to the task." shows. The selection is saved on the project's System Type Selection stage, and replaces what was saved there before. Saved units show Already Added on the page. The project shows them under Selected AC systems. See Review the selected AC systems on the project.
The message says "task", but the selection is saved on the stage.
If something is different
- "Choose a unit for at least one space." or "Choose a quantity for at least one AC system.": choose at least one unit before you save.
- "This project has no System Type stage to save the selection on.": the project has no System Type Selection stage. See Which stages a new project gets.
- "Failed to save products to task", or the save is refused: see I can't save the selection.
- "Airflow: not verified. [reason]": the airflow could not be checked. Select Set design airflow manually. See Set the design airflow.
- Remove one saved unit on this page: on an Already Added unit, select the bin icon, titled "Remove from task". The message "Product removed successfully" shows.
- You used Add All to Task on a combination: see Remove adds a unit, or Add All to Task did not save.