What you see
- A project reads "Not tracked" on Job Costing or on its own page.
- A figure has "est." next to it.
- Contract value is lower than the quotation total.
- Material issued to the project is not in Material actual, or Job Costing warns "[number] project stock-out(s) ... not linked to any project."
- A category is flagged "Cost type not set (reads as Labour)" or "Cost type not set", or an expense counts as labour when it is not.
- You set a cost type and nothing moved.
Why it happens
- "Not tracked": the project has no awarded quotation and no contract value.
- "est.": the figure is estimated.
- Contract value excludes tax. It is the awarded quotations without tax.
- Stock outs with no project count in no project's material.
- A category with no cost type reads as Labour if its key is labour, otherwise as Other. A quotation section with no cost type is sorted by its title.
- A new cost type needs a reload. "Cost type saved. Reload to see the figures move."
- The dates. From and As on limit the cost to that period.
What to do
- For "Not tracked", award the project's quotation. See Accept or reject a quotation.
- For stock outs with no project, select View them on the warning, and check each one. See Issue stock to a project.
- For a category's cost type, select Set type on the project's Summary, choose Material, Labour or Other, and reload the page. See Read a project's job costing.
- For a quotation section counted as the wrong cost type, check the section on the quotation. See Add sections and lines to a quotation.
- Check the From and As on dates.
If it still happens
Read How job costing works out a project's cost and margin. If a figure still looks wrong, submit a request with the project and the figure.
