What you see
"Restricted" in place of an amount:
- in the Value column of the project list;
- on the Contract Value or Estimated Value card of the project page;
- on a Kanban card;
- on the project reports.
On the System Type Selection stage, the grand total of the selected systems is missing.
Why it happens
- "Restricted" in place of a value: your role, or your own settings, do not have Can see selling prices. "Unticked information shows as Restricted."
- No grand total on System Type Selection: your role does not have Can see purchase costs.
What to do
- If you need to see project values, ask your administrator to tick Can see selling prices for your role, or for you. See Restrict what a role can see and export.
- For the System Type Selection total, ask for Can see purchase costs in the same place.
If it still happens
- If the value still reads "Restricted" after the change, submit a request with your name and the project.