What you see

  • A "Limited Editing Mode" notice, and Start Date, End Date and the location fields are greyed out.
  • "Start date cannot be modified for projects in progress or completed"
  • "End date cannot be modified for projects in progress or completed"
  • Project Radius (meters) is greyed out with "Work sessions exist for this project".
  • The client's name, email and phone are greyed out.

Why it happens

  • Dates and location: the project is in progress, completed or has started. Its dates and site are fixed from then on.
  • "Work sessions exist for this project": work sessions are recorded against the project, so the radius stays as it was.
  • Client details: a client record is linked in Select Client. The details come from that record.

What to do

  1. Keep the locked dates and location. Change the other fields as usual and select Update. See Edit a project.
  2. To change the client's name, email or phone, change them on the client record. See Edit a client or mark it inactive.

If it still happens

  • If a date or the site must change, submit a request with the project name and the correct value.