What you see

  • A line under Fulfil has no Issue or no Raise PO.
  • Or Raise PO opens "Access Denied".
  • Or the stock out or the purchase order is refused with one of:
    • "This would exceed the approved quantity: [a] approved, [b] already issued or ordered, so at most [c] more can be issued." (or "ordered")
    • "This line is not approved yet."
    • "This line was rejected; nothing can be issued or ordered against it."
    • "[MR number] is charged to another project." (or "another service contract", or "another service visit")

Why it happens

  • The request or the line is not ready. The request must be Approved, Partially approved or Partially fulfilled, and the line approved with an Open quantity above 0.
  • The line has no catalog item. A free-text line ("Not in the catalog") cannot be issued or ordered until its item is set.
  • The line was rejected, or approved at 0.
  • Too much: the quantity is above the line's open quantity, which is the approved quantity less what was issued and ordered.
  • Another target: the stock out names a different project, contract or visit from the one the request is charged to.
  • Permissions: Issue needs Add on Stock outs; Raise PO needs Add on Purchase orders. Raise PO shows with that box alone, but the purchase order page also needs Purchase Orders, which by default only Owner and Admin hold. A Manager sees the button and lands on Access Denied.

What to do

  1. Check the request's status and the line's Decision and Open. See Material requests: list columns, line quantities and badges.
  2. For a free-text line, set the item first. See Pick or create the catalog item for a request line.
  3. Lower the quantity on the stock out or purchase order to at most the number the message gives.
  4. Keep the stock out on the request's own project, contract or visit.
  5. For Access Denied on Raise PO, ask an Owner or Admin, or someone with Purchase Orders, to raise the order. See Create a purchase order.
  6. If you need Add on Stock outs or Purchase orders, ask your Owner or Admin. See Change what a role can do inside a module.
  7. If more is needed than was approved, raise a new request for the difference. See Raise a material request for a project.

If it still happens

The stock out form has its own rules: the project must not be Tender or Lost, and the stock must be in the warehouse. See Issue stock to a project. If the line still cannot be issued or ordered, submit a request with the request number and the message.