What you see

  • On a project material request, a line shows "Exceeds quotation".
  • Or the line's Quoted reads "Not quoted".
  • Or on the project's Costing tab, Requested (open) is red, with the alert "Open requests exceed quotation: [items]".

Why it happens

A project request compares each line with the project's quotation:

  • Exceeds quotation: the line asks for more of the item than remains of the quoted quantity. Remaining on the line shows what is left.
  • Not quoted: the item is not on the quotation at all.
  • Open requests exceed quotation: across the project's open requests, more of these items is asked for than remains of the quotation.

These are warnings. The request can still be saved and submitted, but it is not approved automatically: an approver decides it. A service request has no quotation, so it never shows them.

What to do

  1. Check the line's Quoted, Issued and Remaining. See Material requests: list columns, line quantities and badges.
  2. If the quantity is a mistake, lower it to what remains, or pick the item that is on the quotation. While it is a draft, see Edit a draft material request.
  3. If the project really needs more, or an item that was not quoted, submit the request with a Note for the approver. The approver may approve it, approve part of it, or reject it.
  4. If the quotation itself should change, an accepted quotation is replaced by a new version. See Supersede an accepted quotation.

If it still happens

If a line says "Not quoted" for an item you can see on the accepted quotation, submit a request with the request number and the quotation number.